Location:
Timmins Gold District, Ontario, Canada
Ownership:
100%
Indicated Gold Resource:
4.3 Million Ounces
Inferred Gold Resource:
0.1 Million Ounces
Metallurgical Gold Recovery
Gold Grade > 1.5 g/t gold: 88.4%
Metallurgical Gold Recovery
Gold Grade > 0.8 g/t gold: 82.5%
Table 1: Fenn-Gib – Economic Model PFS Highlights
The study outlines Mayfair’s strategy to reduce execution risk and prioritizing high-margin material early in the mine plan, supported by a realistic and financeable initial capital outlay. This approach enables rapid value generation from Fenn-Gib while preserving long-term flexibility to deploy free cash flow toward regional growth opportunities or advancing secondary assets to diversify and expand production.
Economic results are presented on an unlevered basis to highlight the strong standalone project returns. Mayfair intends to prudently utilize project-level debt and other financing options to minimize overall cost of capital and maximize per-share economic returns.
Initial capital expenditures are estimated at $450 million, including a 26% contingency on direct costs. The PFS considers a conventional open-pit mining operation and incorporates modular processing plant designs, allowing for a simplified construction schedule of less than 24 months, reducing inflationary and execution risks.
The Project will proceed under the Provincial Class Environmental Assessment (EA) process and does not trigger a Comprehensive EA or federal Impact Assessment under current regulations.
Social and community engagement has focused primarily on the Apitipi Anicinapek Nation (AAN) due to its proximity to the Fenn-Gib site. The Company and AAN have an active Exploration Agreement in place and will continue to advance consultation collaboratively, with the intention of developing a Community Benefit Agreement for the Project.
The Project plans to advance three key strategies in parallel: Ontario-led environmental approvals, Indigenous agreements, and engineering-design-procurement. These initiatives aim to enable major construction within 24–36 months, with commercial operations targeted within five years.
The 2026 PFS assumes an average annual gold production of 71.3 koz over the first 6-years of operation and a total life of mine (“LOM”) production of 920 koz over 14.3 years of operation.
The base case economics have been calculated on an unlevered basis, based on a gold price of US$3,100 and flat exchange rate of C$1.35 per US$ 1. The economics include an effective royalty rate averaging 1.7%, based on all current royalties and encumbrances associated with the reserve at Fenn-Gib.
Free cash flow (“FCF”) after working capital changes is expected to amount to $896M in the first six years of operation. Using a spot gold price of US$4,450/oz (equivalent to $6,123/oz at 1.376 C$/US$ rate) FCF for the first six years of operation is expected to be $1.43 B.
Figure 1: After-Tax Cash Flow (FCF)
The mine plan and associated economics reflect total gold processing of 1.04 Moz with 88.3% recovery. This represents only 24% of the September 3, 2024 Indicated Mineral Resource estimate of 4.3 Moz.
Figure 2: Annual gold production and AISC
The tables below highlight NPV, IRR and payback sensitivity to operating expenses, capital expenditures, foreign exchange rates and the gold price. On average, every US$100 change in the gold price assumption results in an approximate $50 M change in NPV.
Table 2: Sensitivity Analysis
Table 3: Fenn-Gib Mineral Resource Table
The Fenn-Gib Mineral Reserves estimate is based on a design metal price of US$1,750/oz gold and is approximately 25.1 Mt of ore with a gold grade of 1.29 g/t for a contained 1.04 Moz of gold.
Table 4: Fenn-Gib Mineral Reserve Estimate
The initial capital cost (Capex) is estimated at $450 million including $66 million of contingency representing approximately 26% of the direct costs.
The main construction period, excluding early works is estimated at 18 to 24 months.
Sustaining Capital includes mining fleet additions and replacement, highway relocation and future TSF dam raises and associated construction. No provision has been made for potential plant expansion capital.
Table 5: Capital Costs
LOM unit operating costs are estimated at $59.43/tonne of ore processed. Average LOM cash costs and all-in sustaining costs (“AISC”) are estimated at US$1,203 and US$1,292 showing a margin to the base case gold price of US$1,897 and US$1,808/oz Au respectively and a margin on spot gold price of US$3,246 and US$3,159/oz Au.
Table 6: Operating Costs
The PFS outlines a production profile based on a high-grade open pit with a projected operating mine life of 14.3 years, averaging 1.29 g/t Au and an anticipated metallurgical recovery averaging 88.3%. During the first 6 years of operations (years 1-6), annual gold production is expected to average 71,336 oz at a feed grade of 1.47 g/t, with peak output of over 82,000 oz in year 2. The mined Reserves represent only 24% of the overall 4.3 Moz Indicated Mineral Resource.
Figure 3: Gold Production Profile
The Fenn-Gib mine design is based on a conventional truck-and-shovel open-pit operation. The mine plan incorporates an elevated, operating cut-off grade (COG) of 0.8 g/t Au and is structured into three primary mining phases with two smaller satellite pits. Total mined tonnes peak at 16 Mt per year or approximately 44 kt per day.
Figure 4: Mined Tonnage by Material Type[1]
[1] *Mineralized waste is not processed in the PFS mine plan. This material falls below the elevated cut‑off grade used for plant feed but remains above the economic cut‑off grade. At the end of the mine life, approximately 27 Mt of this material is stockpiled at an average grade of 0.51 g/t
Figure 5: Strip Ratio
In total, waste material mined over the LOM is estimated at 152 Mt and will be placed in overburden stockpiles, mine rock storage areas, and utilized in the construction of the tailings storage facility (TSF) embankments.
Figure 6: Fenn-Gib Ultimate Pit Design with Phases
The PFS process plant design for Fenn-Gib is based on metallurgical testwork completed to date and is considered a conventional metallurgical flowsheet to treat gold ore to produce doré bars. The circuit consists of crushing and grinding targeting 80% passing grind size (P80) of 106 µm, sulphide flotation at a mass pull of between 23 to 29%, rougher concentrate regrinding targeting P80 of 13 µm and cyanidation, carbon-in-leach (CIL) adsorption, desorption and regeneration, with cyanide detoxification of the CIL tailings. The design also considers the addition of a gravity concentration circuit in the future. The overall metallurgical recovery of 89.6% Au is expected for a head grade of 1.5 g/t Au.
Figure 7: Process flow diagram
The PFS plant design incorporates modularization concepts for key equipment and infrastructure. Modularization offers several potential benefits, including reduced construction timelines, improved cost predictability, and enhanced quality control through off-site fabrication. This approach also minimizes on-site labour requirements and mitigates weather-related delays, supporting a more efficient and streamlined project execution.
The Fenn-Gib Project infrastructure plan includes all major facilities required for mine development, processing, and support operations. Key components include a process plant with crushing facilities, covered stockpile, and a reagent warehouse, as well as mine maintenance facilities such as a truck shop, wash bay, and warehouses. Essential buildings will be constructed on-site, while non-essential services are anticipated to be located in Matheson.
Site access will be via Highway 101, which connects to the Trans-Canada Highway with regional air service provided by the Timmins Airport. A 5 km segment of Highway 101 will be realigned to ensure a safe clearance from the ultimate pit design. The PFS considers the highway realignment construction following the initial construction phase. This timing will be reassessed in the next phase depending on the timing related to the Ministry of Transport, Ontario approvals.
Tailings and waste management will utilize a paddock-style Tailings Storage Facility (TSF) constructed using a downstream design, which is widely regarded as the preferred approach for long-term stability. The TSF design incorporates extensive site investigations completed as part of the PFS work, ensuring that geotechnical, hydrological, and environmental conditions are fully considered. The facility is engineered for co-disposal of tailings and Potentially Acid Generating (PAG) mine rock, with staged construction and integrated water reclaim systems.
The site layout includes designated mine rock storage areas and overburden stockpiles, along with water management systems designed to capture runoff and seepage. These systems will incorporate water management ponds and a treatment plant.
Construction power requirements of approximately 3 MW will be supplied via a grid connection early in the construction phase, with provisions for emergency backup power to ensure continuity. For operations, the site will require approximately 16 MW of power, with the preferred solution being a Hydro One grid connection through a 27.6 kV line from the Ramore Transformer Station. To mitigate risk in the event of delays to the Hydro One distribution connection or approvals process, the Project has conceptualized an alternate power source as a contingency. The operations power supply includes emergency backup systems as may be needed.
A construction camp (owned and operated by a third-party) is anticipated to be located off-site in Matheson, and no operations camp is planned at this time.
Figure 8: Conceptual PFS Infrastructure and Site Layout
Extensive baseline environmental studies have been underway since 2021, covering terrestrial and aquatic ecosystems, including Species at Risk, groundwater, air quality, noise, geochemical characterization, and cultural heritage resources. Follow-up studies continued through 2025 and are planned to extend into 2026. Results indicate environmental conditions typical of northeastern Ontario, with no critical constraints identified that would prevent mine development. Studies are considered suitably advanced to initiate the environmental approvals process.
The Project is anticipated to proceed through the Provincial Class Environmental Assessment (EA) process and not trigger an Individual EA under provincial requirements or a federal Impact Assessment (IA) under the Impact Assessment Act.
Early engagement with regulators has commenced, and the Company is in discussions with the Ontario government to advance the EA and permitting processes in parallel. It is expected that the Company will submit the required application to the Ministry of Energy and Mines (MEM) regarding participation in the ‘One Project, One Process’ (1P1P) initiative, which facilitates provincial approvals through a dedicated Mine Authorization and Permitting Delivery Team early in 2026.
The Fenn-Gib Project will require permits and approvals typical of mine developments, primarily under provincial jurisdiction. An authorization under the federal Fisheries Act may be required to address potential impacts to fish and fish habitat. A conceptual closure strategy, forming the basis of the Closure Plan, has been developed in alignment with the Mine Rehabilitation Code of Ontario.
Social and community engagement has focused primarily on the Apitipi Anicinapek Nation (AAN) due to its proximity to the Fenn-Gib site. The Project is situated within Treaty 9 territory, approximately 20 km from the AAN community and within their traditional lands. The Company and AAN have an active Exploration Agreement in place and will continue to advance consultation collaboratively, with the intention of developing a Community Benefit Agreement for the Project. In addition, the Project is approximately 17 km from the Town of Black River-Matheson and anticipates utilizing and contributing to the services and infrastructure of the Town. A ‘good neighbour’ agreement with the Town of Black River-Matheson is anticipated.
Engagement with the identified regional Indigenous communities and local stakeholders will commence upon submission of the Environmental Assessment documentation. The Company is committed to transparent communication regarding the Fenn-Gib Project and its environmental design and impacts. The Project is expected to deliver regional benefits through employment, procurement opportunities, and community investment.
Figure 9: High-Level Schedule
The Project plans to advance three key strategies in parallel: Ontario-led environmental approvals, Indigenous agreements, and the engineering-design-procurement phase. These elements will progress concurrently to enable the start of major construction within an estimated 24 to 36 months.
Beginning in early 2026, the Project will move into front-end engineering, followed by detailed engineering and long-lead, critical-path procurement activities. It is anticipated that the Project control estimate will be finalized with 70% to 100% engineering completion and critical construction and supply contracts in place.
Project designs related to environmental aspects of the Project and the permitting tasks are expected to be the critical path for construction commencement.
The Project is envisioned to achieve commercial production within a five-year timeframe.
The Pre-Feasibility Study and Mineral Reserves have an effective date of 19 December 2025 with the Mineral Resource estimate having an effective date of 3 September 2024. The Pre-Feasibility Study was prepared by independent Qualified Persons in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects. The report covers all key aspects of the Project, including property description and location, geology, mineral resource and reserve estimates, mining methods, metallurgical testing and recovery processes, project infrastructure, capital and operating cost estimates, economic analysis, and execution planning.
For readers to fully understand the information in this news release, they should review the technical report that will be filed within 45 days in its entirety, including all qualifications, assumptions, exclusions, and risks. The report is intended to be read as a whole, and individual sections should not be relied upon out of context.
The Qualified Persons (“QPs”) responsible for the Study include:
Full detail of areas of responsibility of the QPs can be found in the Technical Report.
The content of this news release from the Study has been reviewed and approved by the QPs who authored the Study. In addition, Drew Anwyll, P.Eng., Chief Operating Officer of Mayfair, a QP as defined in NI 43-101, has reviewed the PFS on behalf of the Company and has approved the technical disclosure contained in this news release. The full technical report, titled “National Instrument 43-101 Technical Report – Pre-Feasibility Study for the Fenn-Gib Project, Ontario, Canada”, will be filed on SEDAR+ under Mayfair Gold’s profile and will also be available on the Company’s website at www.mayfairgold.ca.
The project is located in the prolific Timmins Gold District in northeast Ontario, 80km east of Timmins, 21km east of Matheson and roughly 10km east of the Black Fox Mine (owned by McEwen Mining). Highway 101 runs right through the project area, giving Fenn-Gib excellent access and infrastructure.
Mayfair Gold has a 100% interest in 21 fee simple patented properties, 152 unpatented mining claims and 144 patented leasehold mining claims located in the Guibord, Munro, Michaud, and McCool Townships in Northeast Ontario, Canada, covering an area of 1,877.8 ha .
Class
Cutoff (Au g/t)
Tonnes
Au (g/t)
Au (oz)
Indicated
>0.7
64,563,000
1.26
2,615,000
–
>0.6
82,125,000
1.13
2,984,000
–
>0.5
105,644,000
1.00
3,397,000
–
>0.4
137,251,000
0.87
3,839,000
–
>0.3
181,302,000
0.74
4,313,000
Class
Cutoff (Au g/t)
Tonnes
Au (g/t)
Au (oz)
Inferred
>0.7
1,140,000
–
>0.6
1,799,000
0.85
–
>0.5
2,710,000
0.75
–
>0.4
4,729,000
0.62
–
>0.3
8,921,000
0.49
Effective date of this updated mineral resource estimate is September 3, 2024. The assay cut-off date for drill holes included in the mineral resource was April 30, 2024.
All mineral resources have been estimated in accordance with Canadian Institute of Mining and Metallurgy and Petroleum (“CIM”) definitions, as required under National Instrument ("NI") 43-101. Mineral Resource Statement prepared by Tim Maunula, P. Geo (T. Maunula & Associates Consulting Inc.) in accordance with NI 43-101.
Mineral Resources reported demonstrate reasonable prospect of eventual economic extraction, as required under NI 43-101. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. The Mineral Resources may be materially affected by environmental, permitting, legal, marketing, and other relevant issues.
Mineral Resources are reported at a cut-off grade of 0.30 g/t Au for an open-pit mining scenario using a 50° pit slope angle. Cut-off grades are based on a price of US$2,000/oz gold, and an open pit mining cost of $3.25/t, process cost of $15.50/t and G&A $2.00/t. Metallurgical recovery of 94% was used. Densities were assigned based on interpreted lithology..
Ounce (troy) = metric tonnes x grade / 31.10348. All numbers have been rounded to reflect the relative accuracy of the estimate.
The quantity and grade of reported Inferred Resources are uncertain in nature and there has not been sufficient work to define these Inferred Resources as Indicated or Measured Resources. It is reasonably expected that many of the Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration.
Tonnages and ounces in the tables are rounded to the nearest thousand. Numbers may not total due to rounding.
Source: Maunula, 2024
Fenn-Gib is located in the southern portion of the Abitibi Sub-province, which is part of the Superior Province of the Canadian Shield. The province is principally composed of volcanic and sedimentary assemblages that have been metamorphosed to greenschist facies and intruded by late tectonic plutons of tonalite and trondhjemite affinity. The property is underlain by the dominantly volcanic Kidd-Munro Assemblage to the north and the dominantly sedimentary Hoyle Assemblage to the south.
Of the several styles of gold mineralization in the property area, the most common consists of quartz-carbonate veins, stringers and breccias hosted within intensely altered volcanic rocks and granitoid instructions. A second style is gold associated with intensely altered sediments with variable fine crystalline pyrite. A third style of gold mineralization is associated with alternation, shearing and sulphidesnsert the Geology Map from the Location section here.
Fenn-Gib is a widely disseminated orebody with an indicated gold resource of 137.3 Million tonnes grading 0.87 g/t gold (0.41 g/t gold cutoff) containing 3.8 million ounces of gold.
Within the larger orebody, there is a higher-grade near surface zone of mineralization that Mayfair is focused on for the initial development of the Fenn-Gib Gold project.
As part of the Company’s preparations to determine final mine design, Mayfair plans to complete a starter pit reverse circulation (“RC”) confidence drill program within the targeted near surface higher grade zone of mineralization at Fenn-Gib. The confidence drilling program is designed to provide improved granularity and additional data on the high-grade zone definition to allow for optimized mine planning and operational predictability at the beginning of mine operations. More accurate data on the zones will help derisk the first few years of operations at Fenn-Gib, which are critical to determine production profile and costs early in the mine life.
The 2025 metallurgical test program commenced in early 2025 and continued through the second quarter. The test work evaluated the performance of fifty composite samples selected to represent the variability of the overall deposit lithologies, across a head grade range of 0.20 to 9.92 g/t gold. The variability test program was designed to evaluate key operational parameters, including flotation feed grind size (comminution), flotation retention time, flotation reagents, concentrate regrinding, and concentrate cyanidation requirements. The insights gained from this test program will support process plant design by informing equipment selection, operational cost estimates, and expectations for overall gold recovery. Testing was undertaken at SGS Laboratories (Lakefield, ON) with the support of Steve Haggarty, P.Eng of Haggarty Technical Services (Burlington, ON). The findings confirmed the suitability of an 80% passing 106-micron product grind size to feed sulphide/gold rougher flotation, determined the optimal flotation retention time, and identified the required concentrate regrind size range (80% passing 9 to14-microns) for gold extraction applying carbon-in-leach (CIL) cyanidation. Metallurgical testing results demonstrate excellent gold recovery in rougher flotation concentrate across all flotation feed grades, achieving between 94-97% recovery of gold to the concentrate. After rougher concentrate regrind and cyanidation, the tests indicate:
The Fenn-Gib gold project hosts a 3.8 million-ounce indicated gold resource (0.4 g/t gold cutoff), which may have the potential to support a large-scale gold development project. However, Fenn-Gib possesses the following unique characteristics that allow Mayfair to target the development of a smaller scale (4,800 tpd) operation:
Creating access and infrastructure for a remote project can be expensive. The existing access and infrastructure of the Fenn-Gib project is a competitive advantage the eases procurement, transportation and the ability to access services and support for the project.
The company is targeting a feed grade of 1.2 – 1.7 g/t gold for the high-grade open pit designs for a 4,800 tpd throughput operation.
2025 Metallurgical test work indicates a gold recovery of 88.4% for higher grade material (>1.5 g/t gold) compared with a recovery of 82.5% for average grade material (>0.8 g/t gold). By starting at 4,800 tpd, mill feed and recovery can both be optimized to improve operating margins.
Larger scale operations tend to have a longer construction schedule. Starting small mitigates the buildup of inflationary pressures (compared with a larger scale operation) and mitigates the potential for execution delays.
This is a lower-risk, disciplined approach to the development of Fenn-Gib. Mayfair expects to begin the Ontario permitting process and complete the PFS for the Fenn-Gib project in 2025. Ontario permitting timelines allow for a potential production decision as early as 2028.
Meaningful engagement with the local communities of Matheson, Timmins and the regional Indigenous Communities are integral to ensure that Mayfair possesses local support to advance the project. The Company acknowledges that the Fenn-Gib project is roughly 10 kilometers from the community of the Apitipi Anicinapek Nation, therefore, Mayfair has a special focus on collaborating with this Nation. This collaboration will be guided by principles of robust environmental stewardship and high-quality design, ensuring that the Project is developed responsibly, with sustainability and respect for the local ecosystem and community at its core.